HZS75 concrete mixing plant is mainly composed of JS1500A concrete mixer, PLD2400 batching machine, cement warehouse and screw conveyor, conveyor belt, and central control room. The mixing machine will use Zenaide Machinery JS series double-horizontal shaft forced mixer, which is a compulsory, high-efficiency equipment, can produce plastic, dry hard concrete and other concrete, high production efficiency, short mixing time, and beautiful appearance, widely used in large, Medium-sized building construction, roads and bridges, and precast plants for the production of concrete products are ideal equipment for the production of commercial concrete.
The theoretical productivity of the HZS75 mixing plant is 75m3/h, the power of the mixing machine is 60KW, the nominal capacity of the mixer is 1500L, the number of bins in the batching machine is 4 cells, the batching capacity is 2400L, 3×100t, and the capacity and capacity of the powder silo capacity are measured. (0 ~ 1500) ± 1% kg, the range and accuracy of admixture weighing (0 ~ 50) ± 1% kg, the accuracy of aggregate weighing ± 2%, unloading height of 3.8 meters, the total installed power of 179.5KW To meet production needs. The central control will realize the fully automated and adopted electronic scale measurement function, with high measurement accuracy and small error. With screen display, ratio storage, automatic compensation for fall and other functions, and equipped with a manual system, can achieve manual and automatic control of the mixing process. In addition, the device is also equipped with a printing system to achieve centralized control and overall management of the entire device.
The storage bin of the HZS75 concrete mixing plant equipment is arranged in a “one” shape. The loader can load materials and can store three kinds of aggregate at the same time. The measured aggregate is conveyed to the main machine via flat belts and lifting systems. According to the user's needs, the powder batching system can be equipped with four powder silos, and the powdered materials are respectively sent from the respective screw conveyors to the corresponding powder weighing hoppers. Water and liquid additives are pumped into the corresponding liquid material weighing hopper.
Advantages
-
Stable & Reliable
6 step protection system ensures safety during operation
Ethernet connections for fast and reliable communications
Computer controlled manufacturing process -
Cost Effective
Lower initial investment for quicker profits
Lower aggregate capacity for lower energy consumption
Lower loader fuel consumption results lower operating costs -
Small & Flexible
Small footprint requires less site space
Enter and exit on both sides. Flexible layout allows setup on any site -
Convenient & Fast
Modular design allows an installation time of only 4 days
Major components can be quickly and easily relocated
Parameter
HZS75 Concrete Mixing Plant | ||
Theory Productivity(m³/h) | 75 | |
Standard Discharging Height(m) | 4.2 | |
Mix Cycle Time(s) | 60 | |
Measurement(m) | 32*14*21 | |
Total Power(KW) | 132 | |
Mixer Model | JS1500A | |
Batching Machine Model | PLD2400 Pneumatic Independent Weighing | |
Belt Width (mm) | 800 | |
Belt Machine Power (KW) | 7.5 | |
Feeding Method | Hopper | |
Weighing Accuracy | Aggregate | ≤2 |
Cement and Ash Coal | ≤1 | |
Water | ≤1 | |
Additive | ≤1 | |
Screw Conveyor Model | LSY219 Italy Technology | |
Silo | 2×100t+1×60t Detachable Silo | |
Control System | Centralized Control | |
MOQ | 1 set | |
Delivery Time | 12days | |
Delivery Port | Qingdao or Tianjin |